LegalDoc
Contracts & Agreements

Force Majeure

Force majeure is a contract clause that excuses a party from performing when something outside their control makes it impossible. It only helps you if it is actually written into the contract.

Create a Service Level Agreementfrom ₦10,000, ready in minutes
F

What force majeure means

Force majeure is the clause that says nobody is in breach when the world gets in the way.

A supplier cannot deliver because a port is closed. A venue cannot host because the state banned gatherings. A contractor cannot build because the site is flooded. If the contract has a force majeure clause covering the event, the affected party is excused rather than liable.

The crucial point, and the one people learn too late, is that Nigerian law does not imply this into your contract. If the clause is not there, you do not have it.

How it is used

A workable clause does four things. It defines the qualifying events, it says what the affected party must do, usually give prompt written notice, it sets out the consequence, normally suspension of obligations, and it says what happens if the event drags on, typically a right for either side to terminate.

When an event hits, the sequence is check whether it falls inside the definition, give notice in the form and time the clause requires, and keep evidence of the disruption. Parties who invoke force majeure months later without notice usually lose the argument even where the event was real.

Key features

  • Must be expressly written into the contract to be available
  • Lists qualifying events, often including natural disasters, war, civil unrest and government action
  • Normally requires prompt written notice from the affected party
  • Suspends performance rather than cancelling the contract outright
  • Usually allows termination if the event continues beyond a stated period

How this works in Nigeria

Nigerian contracts commonly list events with local weight, including civil unrest, communal disturbance, strikes, fuel scarcity affecting logistics, and government action such as import restrictions or a change in regulation.

Currency devaluation and inflation are the interesting battleground. Sellers routinely try to argue that a collapse in the naira excuses them. Unless the clause specifically covers economic conditions, that argument generally fails, because a contract becoming unprofitable is not the same as becoming impossible.

Force majeure vs frustration

Force majeure is contractual. It exists because the parties wrote it, and it operates on their terms.

Frustration is a doctrine of law that applies where an unforeseen event makes performance impossible or radically different from what was agreed, and it is available even without a clause. The catch is that frustration is narrow and rarely succeeds, and where it does apply it kills the contract entirely rather than suspending it.

So force majeure is the flexible, negotiated tool. Frustration is the blunt fallback for parties who did not negotiate one.

Limits and risks

The clause only covers what it lists, and general wording gets read narrowly. A clause listing acts of God and war does not obviously cover a regulatory ban.

It also does not excuse a party who was already in breach before the event, and it does not usually cover events the party could have worked around at reasonable cost. Difficulty and expense are not impossibility.

Worth knowing

Notice requirements are strict. A clause requiring written notice within seven days means seven days, and a party who invokes force majeure late can lose the protection entirely.

Questions people ask

Documents that use this

Force Majeure Clause: Meaning and Use — LegalDoc